Claims on Performance and Payment Bonds in Ohio

posted by Michael Fortney  |  Dec 15, 2009 7:44 PM in Construction Law

Public Improvements

Prime contractors on a public improvement project must furnish a payment bond to the public authority, and thereby agree “to pay all lawful claims of subcontractors, materialmen, and laborers for labor performed or material furnished in carrying forward, performing, or completing the contract; and agree and assent that this undertaking is for the benefit of any subcontractor, materialman, or laborer having a just claim, as well as for the state, political subdivision, district, institution, or agency.”  ORC sec. 153.54(B)(2). 

In order to have a claim on a payment bond on a public improvement, the claimant must comply with ORC sec. 153.56.  The claimant must satisfy the following:

  1. The claimant must have properly prepared and served a notice of furnishing on the prime contractor, unless (a) the claimant’s contract was for an amount equal to or less than $30,000, and (b) the claimant has a contract directly with the prime contractor.
  2. Not later than ninety days after the completion of the contract by the principal contractor and the acceptance of the public improvement by the public authority, the claimant must furnish the sureties on the bond a statement of the amount due to the claimant.

An action may be brought for the amount owed to the claimant 60 days after the notice given to the sureties and within one year of the date that the project was accepted by the public authority.

Private Improvements

Some owners may require prime contractors to furnish a payment bond.  Such a payment bond acts to secure payment to lower tiered subcontractors and suppliers by the prime contractor or surety.  

In the case of a private improvement, the restrictions contained in the payment bond and the contract with the owner govern.  The owner and prime contractor can agree to limit the claimant’s rights to those that the claimant has under ORC Chapter 153, although that is typically not done.

Typically, the requirement for a claim under a private improvement bond are:

  1. Not later than ninety days after the claimant last worked or provided materials on the project, the claimant must notify the prime contractor and the surety of its claim on the bond.
  2. An action may be brought for the amount owed to the claimant within one year of the date that the prime contractor ceased work on the project.

Most Recent Articles

Ohio Court of Appeals Clarifies Time for Serving Notice of Furnishing under Mechanic's Lien Law In a case litigated by Michael L. and Michael R. Fortney of Stark & Knoll, the Court of Appeals for Ohio’s Ni ...
NLRB Declares Chipotle Company Policies Unlawful An Administrative Law Judge (ALJ) for the National Labor Relations Board (NLRB) issued her ruling in the Chipotle case ...
Ohio Court of Appeals Upholds Arbitrator’s Authority When Arguably Construing or Applying Contract A recent ruling by the Ninth District Court of Appeals ruled that a trial court cannot vacate an arbitration award beca ...
Ohio Supreme Court Upholds Liquidated Damages Provisions in Construction Contracts The Ohio Supreme Court overturned the Fourth District Court of Appeals' holding that a $700 per day liquidated dama ...
2nd Circuit Agrees with NLRB; Facebook "like"s are Protected Activity In 2014 the National Labor Relations Board (NLRB) issued its ruling in  Triple Play Sports Bar . It decided that&n ...